The New Jersey Department of Transportation (NJDOT) has announced a four-month closure of the Route 71/Main Street drawbridge over the Shark River. The closure, affecting travel between Belmar and Avon-by-the-Sea, is scheduled to begin at 5 a.m. on Tuesday, October 14, and will last until late February 2026. The shutdown is required to perform permanent repairs on the bridge's aging mechanical systems.
Key Takeaways
- What: Full closure of the Route 71/Main Street drawbridge.
- When: From 5 a.m. Tuesday, October 14, until late February 2026.
- Where: The bridge connects Belmar and Avon-by-the-Sea in Monmouth County.
- Why: Permanent repairs to the bridge's mechanical operating systems.
- Alternative Travel: Vehicles will be detoured to Route 35. A free shuttle will be provided for pedestrians and cyclists.
Bridge Closure for Essential Mechanical Upgrades
The upcoming four-month closure is part of a critical project to address long-standing issues with the 92-year-old drawbridge. According to an official press release from the NJDOT, the work is necessary to make permanent repairs to ensure the bridge's functionality and safety. This follows a period of interim repairs conducted during the spring and summer after a mechanical malfunction.
The malfunction prevented the bridge from opening correctly for marine traffic. Since maritime vessels have the legal right-of-way, the NJDOT was forced to keep the bridge in the open position, which detoured vehicle, pedestrian, and cyclist traffic for an extended period. The new repairs are designed to prevent similar failures in the future.
Project Scope
The core of the repair work involves replacing outdated mechanical components. Because original parts for the 1932 structure are no longer available, engineers will install a modern hydraulic piston system on the bridge's south leaf. This upgrade is expected to provide a more reliable and durable mechanism for opening and closing the drawspan.
Detour Routes and Shuttle Service Information
During the four-month construction period, all traffic will be redirected. The NJDOT has established specific alternative routes for vehicles and a dedicated shuttle service to accommodate pedestrians and cyclists who rely on the crossing.
Vehicle Traffic Detour
All drivers attempting to cross the Shark River via Route 71 will be detoured to the nearby Route 35/Shark River Bridge. Motorists are advised to plan for potential delays and allow for extra travel time, especially during peak commuting hours. Signage will be in place to guide drivers along the alternate route.
Free Shuttle for Pedestrians and Cyclists
To maintain connectivity between Belmar and Avon for non-motorized traffic, a free shuttle bus service will be in operation. The service is designed to be accessible and convenient for daily commuters and local residents.
"This four-month closure is necessary to make permanent repairs to the bridge," the New Jersey Department of Transportation stated in a press release, highlighting the importance of the project.
The shuttle will run continuously from 8 a.m. to 8 p.m. every day of the week throughout the construction period. Each complete loop is estimated to take between 30 and 35 minutes. The vehicle is ADA-accessible, has 20 seats, and is equipped to transport bicycles.
Long-Term Plans for the Bridge
While these repairs will extend the operational life of the current bridge, they are a temporary solution. The NJDOT has confirmed that a full replacement of the Route 71 drawbridge is planned. According to the department, the final design for the new bridge is expected to begin in 2026. Construction is slated to start in 2028, with an anticipated completion date in 2031.
Complete List of Shuttle Bus Stops
The shuttle will follow a set route with multiple stops in both municipalities to serve key locations, including the Belmar train station. The designated stops are clearly marked to ensure ease of use for the public.
Stops in Belmar:
- The Belmar train station at West Railroad Avenue and 10th Avenue
- Main Street and 10th Avenue
- Main Street and Eighth Avenue
- Main Street and River Road
- West Railroad Avenue and Seventh Avenue
Stops in Avon-by-the-Sea:
- Main Street and Sylvania Avenue
- Main Street and Washington Avenue
- Main Street and Jefferson Avenue
- Main Street and Garfield Avenue
Residents and travelers are encouraged to check the NJDOT website for any updates or changes to the construction schedule or shuttle service throughout the four-month period. The project represents a significant investment in local infrastructure aimed at improving reliability for both road and river traffic in the long term.